A flood control project at Pleasant Valley dam is projected to cost $2,000,000 today, have annual maintenance

A flood control project at Pleasant Valley dam is projected to cost $2,000,000 today, have annual maintenance costs of $50,000, and have major inspection and upkeep after each 5-year interval costing $250,000. If the interest rate is 10%/year, what is the total capitalized cost of the project?